Place : Nasu-machi, Tochigi
Dimension : two storied house, 53tsubo
Structure : Wooden and RC
Architect & supervision:
A.TERA architect & associates
Designing term : Jan/06- Oct/06
Constructor : Fukaya-kensestu co., Ltd.
Construction term : Nov/06- Apr/07
|
|
 |
| 31/Jan/07
|
| Completion of Framework
On Jan. 30th, a lucky day called
"Kichijitsu"in Japan, I was present
at the construction site of completion of framework.
The constructors worked using 10 ton of a tow
truck. But a tow truck's arm couldn't reach the
back of the site. Therefore all of the carpenters
carried member of framework by hand and finally
completion of framework finished. The wing is
good height related surround.
Next day, it was very clear and warm day as felt
sweaty, only January! The carpenters set up the
rafter and sheathing.
Mr. Ebe, a foreperson of Fukaya kensetsu, is pictured
right. Mr. Usui, a master carpenter, is pictured
left.
"I have never been experienced this warm
winter!" Mr. Usui said. Because They had
much snow in last January in Nasu. (as picture)
I wish it won't snow hard on February.
|



|
| 17/Jan/07 |
Backfill
The demolish of the formwork has finished, the constructor
started backfill of the drilled soil. The construction
site fall towards the back from the road and the
back level is about 2M higher than a road level.
We use the difference of elevation to plan this
house like buried into a slope.
|

|
| 16/Jan/07 |
Dismantlement
of formwork
The construction started from 6th, Jan.
The formwork was dismantled melting snow layer about
20 cm, it has been completed. The finish of concrete
is perfect. We are looking forward to seeing the
view from 2nd floor.
|


|
| 27/Dec/06 |
Cast
concrete
We worried about today's weather due to day-old
low atmospheric pressure, but it was clement day
for casting concrete. After the final check of layout
of reinforcement in the morning, the constructors
cast concrete.
In Nasu, the temperature is around 10 degrees in
the daytime, but at night it drops down to about
0 degrees. We combined concrete and "freeze
proofing agent" to avoid freeze.
So if the temperature will drop down about 10 degrees.
The agent makes concrete keep the effectual temperature
for the construction.
We will use the New Year's holidays to do concrete
cure until 5th, Jan.
|


|
| 26/Dec/06 |
|
The layout of reinforcement inspection
Under rainy skies and rigid conditions as temperature
is 2 degrees, the constructors had working. For
tomorrow's casting concrete, we did the layout
of reinforcement inspection.
Mr. Nakahara of Nakahara architect's office, as
a structural architect ran a check on it.
He rapidly checked the main points such as the
fixing length of the reinforcing, with the specialist's
eyes.
And we directed the constructors to care about
the temperature management.
It is one of the factors as in determining of
the good concrete or not.
After tomorrow's casting concrete,
the construction in this year will end.
|

|
| 19/Dec/06 |
|
1 Floor; Layout of reinforcement
and formwork
The work of layout of reinforcement and formwork
had been well on.
The constructors had worked toward casting concrete
scheduled for on 27th in the cold weather as numb
fingers.
I called to them "Thanks for a job well done."
And they said smiling "We feel good when
it is this cold. So it makes good progress!"
Such confidence! I take off my hat to their sprit.
But we faithfully checked their work, such as
size, number, pitch and the fixing way of the
layout of reinforcement. They passed this check.
On December 26th, we are going to check the layout
of reinforcement of 2nd floor.
|


|
| 15/Nov/06 |
|
Confirmation of the site and
start excavation work
As cutting of trees had completed, the excavation
work started. We checked the ground plane from
a test pit. As a result, we could confirm assumed
supporting soil.
|


 |
| 2/Nov/06 |
|
Ceremony for sanctifying ground
With attendance of the clients, the constructors
and us, the ceremony was held by Kuroiso shrine.
After then, we checked the layout of a new house,
site level and unwanted trees by reference to
the rope which was set up along a building line.
|
 |
 |
|
|
 |
 |
|
 |
 |
 |
 |
|
|
[ last update 2002-07-01 ]
|
 |
|